Question #: 13
Topic #: 1
[All PMI-ACP Questions]

An agile practitioner wants to ensure that stakeholders have current information about a project's progress.
What should the agile practitioner do?

  • A. Regularly circulate an updated, detailed version of the project plan
  • B. Frequently update the online project management office (PMO) repository site
  • C. Invite the stakeholders to daily stand ups
  • D. Post a project board in an area where all can view it
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
snow5
Highly Voted 4 years ago
D is true, is part of Info / Comm radiator
upvoted 6 times
...
josephsafiran
Most Recent 2 weeks, 4 days ago
Selected Answer: D
D is correct
upvoted 1 times
...
Imrangoshi
1 year, 2 months ago
Selected Answer: D
D is the Correct Answer
upvoted 1 times
...
Boolie
1 year, 7 months ago
Kanban!
upvoted 1 times
...
cutri89
1 year, 7 months ago
Selected Answer: D
d right
upvoted 1 times
...
InvisibleBeing
1 year, 10 months ago
Selected Answer: D
D is correct. Transparency
upvoted 1 times
...
7029
1 year, 10 months ago
Selected Answer: D
D is the most
upvoted 1 times
...
richck102
2 years, 4 months ago
D sure
upvoted 1 times
...
aws_guru1
3 years, 1 month ago
D is the answer - Information Radiator
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...