Actual exam question from PMI's PMI-ACP
Question #: 18
Topic #: 1
[All PMI-ACP Questions]

An agile coach realizes that a team responsible for a major release is a few months behind schedule. The marketing department is unaware of this delay, and is planning to start the marketing campaign and announce the release.
What should the agile coach do?

  • A. Meet with the agile team lead to discuss ways to improve the team velocity and get back on track
  • B. Use this as a learning opportunity and allow the team to handle the situation when the marketing campaign begins
  • C. In the upcoming retrospective, discuss ways to improve sharing project status information
  • D. Meet with the marketing stakeholders to explain that the team will miss the planned release date
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
astrologic
Highly Voted 2 years, 8 months ago
Selected Answer: C
An agile coach helps organizations, teams, and individuals adopt agile practices and methods while embedding agile values and mindsets. The goal of an agile coach is to foster more effective, transparent, and cohesive teams, and to enable better outcomes, solutions, and products/services for customers. C is right answer
upvoted 7 times
...
ramune110
Most Recent 3 weeks, 6 days ago
Vote C
upvoted 1 times
...
ELTIGANI
2 months ago
Selected Answer: D
This option ensures that the marketing department is informed promptly about the delay, allowing them to adjust their plans for the marketing campaign and release announcement accordingly. It demonstrates transparency and proactive communication, which are crucial in maintaining trust and managing expectations among stakeholders.
upvoted 3 times
...
FaisalK76
5 months, 2 weeks ago
Selected Answer: A
A is the right answer. The team has to find ways to bring the project back on track.
upvoted 1 times
aqz_111
2 months ago
Agile is working in a trust environment. not 'push' so A is not correct. The question has a communication issue. so...how to resolve and improve
upvoted 1 times
...
...
janojano
7 months, 2 weeks ago
Selected Answer: D
It's a few months behind schedule, that's pretty significant, and MKT does not know about this delay. I vote for D., I think it's most important to communicate the actualized delay.
upvoted 3 times
ImGonnaPassIt
5 months, 3 weeks ago
That would be correct it the question would be "What Product Owner should do"
upvoted 2 times
aqz_111
2 months ago
yes, the first step is to communicate with marketing department about the delay, otherwise, once the release is announced but nothing to deliver. the second step is to discuss with team member how to improve in retrospective so C is not the first thing to tackle the immediate issue
upvoted 1 times
...
...
...
ImGonnaPassIt
8 months, 1 week ago
Selected Answer: C
Product Owner is the one who communicates to the Customer, not Agile Coach. The question states what Agile Couch to do. Agile Coach will work with the team so the answer C. However, this Agile Coach to inform Product Owner about the delay and this is within PO responsibility to handle this with the Customer. The answer D is correct from the Product Owner perspective only. I vote C.
upvoted 1 times
...
Michaela0015
8 months, 1 week ago
Selected Answer: C
C - correct. I agree with the explanation that Agile coach is not responsible for informing stakeholders. That's Product owner's job.
upvoted 1 times
...
Kmad756
10 months, 2 weeks ago
I think Answer should be "C" regardless of the situation. Corrective actions on an agile team is discussed during the retrospective which is related to agile. Communicating with marketing team etc is not relevant here as I see.
upvoted 1 times
...
Red_Apple1
1 year ago
Selected Answer: A
A. Ask the opinion of key stakeholders and the client to ensure the correct approach is being used
upvoted 1 times
...
Imrangoshi
1 year ago
Selected Answer: C
C is the Correct Answer
upvoted 1 times
...
wail84n
1 year ago
the Product owner has to set with stakeholders not the coach
upvoted 2 times
...
Vedantp
1 year, 1 month ago
Selected Answer: A
The Product Owner is responsible for providing project status/updates to the stakeholders and not the Scrum Master.
upvoted 1 times
...
Siwana
1 year, 3 months ago
Selected Answer: D
O atraso jáacontecu.
upvoted 2 times
...
Agile_Dario_Conde
1 year, 3 months ago
Selected Answer: D
C requires waitng which is a waste in Lean, D is the best answer.
upvoted 2 times
...
Raksim
1 year, 5 months ago
..release is in a few months means: it will be carried out in the coming iterations, so there will be at least one retrospect in between, allowing the team to discuss the issue. Keyword UNAWARE - solution = find ways to improve information sharing: C.
upvoted 1 times
...
abhi517
1 year, 5 months ago
Selected Answer: D
D. Meet with the marketing stakeholders to explain that the team will miss the planned release date. The agile coach should communicate the delay to the marketing department to manage their expectations and avoid false promises or disappointments. The team should also work on improving their velocity and finding ways to get back on track, but communicating the delay to stakeholders is crucial.
upvoted 1 times
...
cutri89
1 year, 5 months ago
Selected Answer: C
i thik this
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...