Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 61 discussion

Actual exam question from PMI's PMI-ACP
Question #: 61
Topic #: 1
[All PMI-ACP Questions]

A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.
What should the team do?

  • A. Estimate only functional requirements that will impact product quality
  • B. Add team resources
  • C. Refer the issue tot eh product owner
  • D. Break non-functional requirements into those that can be delivered in the given sprint
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
JftCoCo
1 month, 2 weeks ago
Selected Answer: D
I think the answer is D, cause let the team address this requirement first.
upvoted 1 times
...
chlaithem
10 months, 1 week ago
Selected Answer: C
While breaking down the non-functional requirement (D) also holds merit, the most crucial initial step is open communication and involving the product owner in the decision-making process
upvoted 2 times
...
Petrevski
1 year, 7 months ago
Selected Answer: D
D = correct.
upvoted 2 times
...
Smokeyofficiial
1 year, 8 months ago
Option D. The team should work together to identify which non-functional requirements can be delivered within the sprint's capacity and prioritize them accordingly. This approach ensures that the sprint delivers value while also meeting the project's requirements and objectives. If necessary, the team can work with the product owner to adjust the project's scope or prioritize non-functional requirements in future sprints.
upvoted 2 times
...
InvisibleBeing
1 year, 10 months ago
Selected Answer: C
I am going with C. D does not make sense. Why would you break up non-functional requirements to see what can be delivered this sprint? The question is clear about the importance and the question states that it MUST be delivered. Keeping in mind that it is a MUST requirement, I think best option is C. Even though I am aware of the fact that: While the Product owner indicates the features that need to be developed, the Sprint backlog is owned by the Development team. The dev team selects the number of items from the top of the product backlog that they think they can complete in one sprint. If the team feels like the items are too much to be completed in one sprint, the team then negotiates the scope of the sprint with the PO.
upvoted 3 times
InvisibleBeing
1 year, 10 months ago
The PO needs to be consulted for which PBIs to remove in order to accommodate the non-functional requirement. It is the PO who will decide what is important and what is not important for this Sprint. The Dev Team is the sole decision maker when it comes to how many points or how many stories they can complete in one sprint.
upvoted 1 times
...
...
zzw890827
2 years, 1 month ago
D makes sense.
upvoted 1 times
...
minwang
2 years, 2 months ago
I believe C is the right answer
upvoted 1 times
...
richck102
2 years, 4 months ago
D sure
upvoted 1 times
...
JackNguyenvn
2 years, 7 months ago
D is correct
upvoted 1 times
...
RKarpe
3 years ago
An imp NFR is expected to be delivered in the sprint. If the NFR is split, and only few of the features are delivered in the current sprint, it means that the entire NFR is not delivered which is the actual ask. in that case, PO should be informed. Should be C
upvoted 2 times
...
adelshenouda
3 years, 3 months ago
Suggests D
upvoted 1 times
...
Alaaradwan
3 years, 4 months ago
D right answer
upvoted 1 times
...
HTTPS
3 years, 5 months ago
I would go for D.
upvoted 1 times
...
Athena75
3 years, 8 months ago
Answer is C. Even if it's a MUST is must be logged to the Product Backlog, prioritized and approved by the PO
upvoted 2 times
Athena75
3 years, 8 months ago
Correction, The answer is D
upvoted 3 times
...
...
navingthomas
3 years, 9 months ago
Please note that "team" consists of dev team, SM and the PO. Now read the question again. Answer is D
upvoted 4 times
...
snow5
4 years ago
C is the right answer. A& B are not applicable. D is talking about all NFRs while the question is focusing on an important NFR, so the best way in such case is to refer to PO to decide
upvoted 1 times
srv3
3 years, 11 months ago
I assume that D is right answer. Even if you inform PO about that, there is no other way to complete NFR than split it into 2+ iterations.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...