Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 80 discussion

Actual exam question from PMI's PMI-ACP
Question #: 80
Topic #: 1
[All PMI-ACP Questions]

During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested.
What should the agile practitioner do?

  • A. Work with the agile team and product owner to agree on the definition of done
  • B. Ask the sponsor to determine whether the product is completed
  • C. Plan another review after the product has been tested
  • D. Add testing to the backlog, and have the product owner reprioritize
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
HTTPS
Highly Voted 3 years, 3 months ago
A - Correct From The Scrum Guide: “The Definition of Done creates transparency by providing everyone a shared understanding of what work was completed as part of the Increment. If a Product Backlog item does not meet the Definition of Done, it cannot be released or even presented at the Sprint Review. Instead, it returns to the Product Backlog for future consideration.”
upvoted 6 times
...
azzain
Most Recent 3 weeks, 5 days ago
A. The agile practitioner should work with the agile team and product owner to agree on the definition of done. This ensures that everyone has a shared understanding of what constitutes a completed product, including all necessary steps such as testing. • Clarifies completion criteria: A clear definition of done ensures that everyone on the team understands what it means for a product to be complete. • Prevents misunderstandings: By agreeing on a definition of done, the team can avoid future conflicts and misunderstandings about the completion of products. • Ensures quality: A well-defined definition of done helps to ensure that products are delivered to a high standard of quality.
upvoted 1 times
...
Petrevski
1 year, 5 months ago
Selected Answer: A
A = correct
upvoted 1 times
...
Minhha3
1 year, 5 months ago
Vote A
upvoted 1 times
...
Smokeyofficiial
1 year, 6 months ago
Option A. In Agile Framework, the definition of done is a shared understanding between the team and the product owner of what it means for a product increment to be considered complete. It includes a set of criteria that the product must meet, including testing, to ensure that it is ready for release. In this scenario, the team and product owner have different understandings of what it means for a product to be complete. The Agile practitioner should work with the team and product owner to agree on the definition of done that includes testing as a necessary criterion.
upvoted 1 times
...
InvisibleBeing
1 year, 7 months ago
Selected Answer: A
A is correct.
upvoted 1 times
...
minwang
2 years ago
I vote C
upvoted 1 times
...
richck102
2 years, 2 months ago
A sure
upvoted 2 times
...
JackNguyenvn
2 years, 5 months ago
A is correct
upvoted 2 times
...
snow5
3 years, 10 months ago
Answer is D not C, Ref: Mike Griffiths, PMI-ACP Exam Prep Ed 1st "When the development team is demonstrating their User Stories completed, the Product Owner could accept the User Story there and then, or may provide feedback which then results in an amended or new User Story. As this is the end of the Sprint, any User Stories not completed go back into the Product Backlog. "
upvoted 1 times
srv3
3 years, 9 months ago
I assume that A is correct answer. Testing is not about certain user story or certain activity. It's about common requirement for that product/project. If testing is required then more likely it's about all product/project but not specific user story. So it shoud be described as Definition of Done. Even if it relates to certain user story, then it is acceptance criteria but not additional user story or backlog item.
upvoted 7 times
...
...
snow5
3 years, 10 months ago
C is the answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...