A project is starting and the type of work is complex and suitable for agile. In assessing the team members, it appears that co-location would be a challenge. What should the agile practitioner do?
A.
Select and implement collaboration tools to augment team interactions
B.
Provide each geographical area with their own product owner and divide the work between the teams
C.
Increase the number of requirements documents and ensure they are clearly communicated
D.
After several sprints, calculate velocity based on primary team location and use secondary team as reserve
Option A.
Agile methodology values face-to-face communication and collaboration among team members, but co-location may not always be possible due to various reasons such as geographical dispersion. In such situations, it is recommended to use collaboration tools to facilitate team interactions, such as video conferencing, instant messaging, and online collaboration platforms. These tools can help bridge the gap between geographically dispersed team members and enable them to work collaboratively and efficiently.
In this usecase scenario, it is not mentioned explicitly as multiple teams. More POs comes into picture only during multiple teams are there for a single product. So B may not be an option and A makes sense
upvoted 1 times
...
...
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Petrevski
1 year agoSmokeyofficiial
1 year, 1 month agoInvisibleBeing
1 year, 3 months agorichck102
1 year, 9 months agosnow5
3 years, 5 months agoGPena
3 years, 5 months agoAbdulafou_K
3 years, 5 months agoSrinath_C
7 months, 3 weeks ago