Exam PMI-ACP topic 1 question 166 discussion

Actual exam question from PMI's PMI-ACP
Question #: 166
Topic #: 1
[All PMI-ACP Questions]

A scrum team has eight developers, but only two are database engineers. During the last few retrospectives, the team identified that most sprint stories are dependent upon database engineers. This has created a bottleneck in completing stories.
What should be proposed to the team?

  • A. Have other team developers attend training to learn database skills
  • B. Monitor the retrospectives of two additional sprints before taking action
  • C. Plan fewer stories for the sprint to reduce the database engineer's workload
  • D. Ask the scrum master to work the product owner to remove backlog stories that have database dependency
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
srv3
Highly Voted 3 years, 9 months ago
A is the best answer, bcz: 1. few sprint past and issue is highlighted. 2. root cause is lack of database expertise in the team 3. team should be self-sufficient so additional DB expertise is required. A) is the only way to get it.
upvoted 8 times
...
thewalker
Most Recent 2 weeks, 6 days ago
Selected Answer: A
A. Have other team developers attend training to learn database skills By training other developers to acquire database skills, the team can distribute the workload more evenly and reduce dependency on the two database engineers. This approach not only alleviates the bottleneck but also increases the team's overall flexibility and capacity to handle database-related tasks.
upvoted 1 times
...
janojano
7 months, 4 weeks ago
Selected Answer: A
The reason why A. is the best answer, is because in Agile/Scrum you aim to have cross-functional self-organizing development teams. A good way to attain that while maintaining the same Team is with cross-training.
upvoted 1 times
...
tThye
1 year, 3 months ago
Why not B or C?
upvoted 1 times
Petrevski
1 year, 1 month ago
Because you won't solve the issue (there still gonna be a lack of DB engineers)
upvoted 1 times
...
...
Petrevski
1 year, 4 months ago
Selected Answer: A
A = correct
upvoted 1 times
...
Minhha3
1 year, 5 months ago
Vote A
upvoted 1 times
...
richck102
2 years, 2 months ago
B sure
upvoted 1 times
...
thuha1704
2 years, 6 months ago
A is my answer
upvoted 2 times
...
Deer
3 years ago
My answer is A
upvoted 1 times
...
aws_guru1
3 years ago
A seems to be the best answer for me - cross training.
upvoted 1 times
...
Admirable
3 years, 2 months ago
Agile promotes cross training. The best answer is A.
upvoted 2 times
...
STW
3 years, 3 months ago
Why not C? That should reduce the bottleneck.
upvoted 1 times
...
snow5
3 years, 10 months ago
the question is subjective ! Both A&B could be chosen
upvoted 1 times
...
mikyngure
3 years, 10 months ago
A rather
upvoted 3 times
...
mikyngure
3 years, 10 months ago
Answer should B
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel