Exam PMI-SP topic 2 question 116 discussion

Actual exam question from PMI's PMI-SP
Question #: 116
Topic #: 2
[All PMI-SP Questions]

You are project manager of HHK project. Examine the network diagram given below:

A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based on the project network diagram, how many days can Activity E be delayed?

  • A. Four days
  • B. Six days
  • C. Five days
  • D. Zero, it is on the critical path.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Activity E has four days of float. The entire project will take 19 days to complete. Float, also called slack, is the amount of time an activity can be delayed without affecting any subsequent activities. There are two types of floats available: Free Float: It is the amount of time a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities. Total Float: It is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating schedule constraint. Float is calculated by using the critical path method technique.
Incorrect Answers:
B, C: These are incorrect calculations of the amount float available for Activity
D: Activity E is not on the critical path.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tauseefnaz
4 years ago
this answer is wrong, Actvity E was delayed due to mentioned reasons in question and took 10 days, so D is right Answer
upvoted 2 times
ed55bcd
8 months, 3 weeks ago
I agree with you
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.