Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 183 discussion

Actual exam question from PMI's PMI-ACP
Question #: 183
Topic #: 1
[All PMI-ACP Questions]

A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues.
What should the team do?

  • A. Capture risks and make them visible, and use a burndown chart to focus on reducing risks early in the project
  • B. Ask the scrum master to extend the sprint's duration to allow more time to work through technical issues
  • C. Place the impacted stories on the story board, and use daily stand ups to make the product owner aware of the technical issues
  • D. Seek guidance from the development manager
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
2 weeks, 5 days ago
Selected Answer: A
Risk Visibility: Capturing and making risks visible ensures that the entire team is aware of potential issues and can monitor them closely. Burndown Chart: Using a burndown chart to track and focus on reducing risks helps the team to prioritize risk mitigation activities and measure their progress. Proactive Management: This approach allows the team to address technical issues early in the project, reducing the likelihood of significant delays or failures later on. Team Collaboration: Making risks visible fosters a collaborative environment where team members can work together to find solutions and support each other in overcoming technical challenges. Continuous Monitoring: Regularly updating the burndown chart and reviewing risks ensures that the team remains focused on mitigating risks throughout the project.
upvoted 1 times
...
Petrevski
1 year, 4 months ago
Selected Answer: A
B = wrong. The SM cannot extend the sprint's duration and allow something. C = wrong. What is a story board? Daily stand ups to make PO aware of the technical issues? D = wrong. A development manager? Not an agile role. A = correct. Maye is not the best option, but the most logical offered answer.
upvoted 2 times
...
InvisibleBeing
1 year, 7 months ago
Selected Answer: A
A is correct. First of all, let me discuss if the PO can attend the daily scrum or not. Basically, the daily scrum is for the development team. The SM or the PO can attend the daily scrum if they are working on PBIs. They can also attend as observers. There are comments below suggesting PO cannot attend the daily scrum. Another point. please be careful to note the difference between daily stand-up and daily-scrum. Daily stand-up is an event in XP programming without the scrum rules. When you are answering questions please see if it is XP or scrum. This question does not say "scrum-team", in this case we can assume this to be either scrum or XP. Scrum has product owners, but XP does not. XP has daily standups and scrum has daily-scrum.
upvoted 1 times
InvisibleBeing
1 year, 7 months ago
Scrum guide does not mention anywhere that PO and the SM cannot attend the daily scrum.
upvoted 1 times
InvisibleBeing
1 year, 7 months ago
The reason why option C is not the correct answer because option C talks about placing the impacted stories themselves on the board. Placing just the impacted stories do not make the risks and the plans to handle the risks visible. Risks need to be visible at all times along with the mitigation plan and the risk owner. Capturing risks separately allows you the opportunity to track and monitor risks.
upvoted 1 times
...
...
...
GrandMasta
2 years ago
Only the Dev Team members are required for the Daily Scrum. The product owner does not participate on the daily scrum. If he does attend, he does so as an observer. Only the developers are allowed talk and participate. Hence the answer is A
upvoted 2 times
InvisibleBeing
1 year, 7 months ago
You are WRONG. Kindly please don't comment on something you do not have the complete knowledge. Please read the scrum guide again.
upvoted 2 times
...
...
Eli8
2 years, 1 month ago
I go for (C). The significant amount of uncertainty has been an issue needs to announce PO in daily scrum. Agile principle6: The most efficient and effective method of conveying information to and within a development team is face-to-face conversation. Eliminate (A) because only capture the issue and monitor it solve nothing.
upvoted 1 times
...
Eli8
2 years, 1 month ago
I go for (D). The significant amount of uncertainty has been an issue needs to announce PO in daily scrum. Agile principle6: The most efficient and effective method of conveying information to and within a development team is face-to-face conversation. Eliminate (A) because only capture the issue and monitor it solve nothing.
upvoted 1 times
Eli8
2 years, 1 month ago
Correct C
upvoted 1 times
...
...
Eli8
2 years, 1 month ago
I go for (D). The significant amount of uncertainty has been an issue needs to announce PO in daily scrum. Eliminate (A) because only capture the issue and monitor it solve nothing.
upvoted 1 times
Eli8
2 years, 1 month ago
Correct C
upvoted 1 times
...
...
richck102
2 years, 2 months ago
i vote A
upvoted 1 times
...
Kiran_Varri
2 years, 5 months ago
agree...via elimination, C definitely does not make the cut !! Product owner does not attend the daily stand up right?
upvoted 1 times
GrandMasta
2 years ago
You are correct.
upvoted 1 times
...
...
JackNguyenvn
2 years, 5 months ago
A is the right answer
upvoted 3 times
...
Dsugandhi
3 years, 3 months ago
A - Issues in agile means risks, which occurred. Agile team should mitigate high risk high value as early as possible.
upvoted 3 times
...
javid880
3 years, 7 months ago
daily stand ups and PO ?. guess A is the answer
upvoted 4 times
...
srv3
3 years, 9 months ago
A. Capture risks and make them visible, and use a burn down chart to focus on reducing risks early in the project. > seems to be the best answer because team proactively manage risks and reduce risk early in the project. C. Place the impacted stories on the story board, and use daily stand ups to make the product owner aware of the technical issues. > where the stories were before? Out of story board? Simple informing P.O. does not mean any other activities by itself. Also not sure
upvoted 3 times
...
snow5
3 years, 10 months ago
through reviewing different sources I found C is the right answer, but still not sure !
upvoted 1 times
...
GPena
3 years, 10 months ago
A is the right answer
upvoted 3 times
...
tsangckl
3 years, 11 months ago
The answer should be A
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...