Exam PMI-ACP topic 1 question 190 discussion

Actual exam question from PMI's PMI-ACP
Question #: 190
Topic #: 1
[All PMI-ACP Questions]

Midway through a two-week sprint, an agile team realizes that the features cannot be delivered within the sprint. The team determines that another week will be required to complete all committed features.
What should the team do?

  • A. Plan for overtime, and include the effort as part of the estimation
  • B. Increase team velocity to deliver more story points
  • C. Identify the reason for over-commitment to the sprint and create an action plan for the following sprint
  • D. Add resources to assist with sprint execution
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
snow5
Highly Voted 3 years, 9 months ago
Any incomplete stories will be taken back to PBL, period, Adding new resources is risky and costly, and makes no sense for having timebox. So C is the most appropriate answer.
upvoted 9 times
...
tsangckl
Highly Voted 3 years, 11 months ago
It should be C
upvoted 7 times
...
thewalker
Most Recent 2 weeks, 5 days ago
Selected Answer: C
Understanding Over-commitment: The team should analyze why they over-committed. This could involve looking at estimation errors, unexpected complexities, or unforeseen issues. Learning and Adapting: By identifying the root cause, the team can adjust their planning and estimation processes to avoid similar issues in the future. Continuous Improvement: Agile methodologies emphasize learning from each iteration. Creating an action plan for the next sprint ensures that the team continuously improves their processes. Maintaining Sprint Integrity: Extending the sprint or adding resources can disrupt the rhythm and predictability of the sprint cycle, which is not advisable in agile practices. Focus on Value Delivery: The team should prioritize delivering the most valuable features and possibly defer less critical ones to future sprints.
upvoted 1 times
...
Petrevski
1 year, 4 months ago
Selected Answer: C
C = correct. Every other offered option is not an agile approach.
upvoted 1 times
...
InvisibleBeing
1 year, 7 months ago
Selected Answer: C
C is correct.
upvoted 1 times
...
richck102
2 years, 2 months ago
C sure
upvoted 1 times
...
JackNguyenvn
2 years, 5 months ago
C is correct
upvoted 2 times
...
snow5
3 years, 10 months ago
I go with C
upvoted 4 times
...
GPena
3 years, 10 months ago
The best way is to add resources as you have a commitment with the goal. If you extend a week or more you will no comply with the stakeholders expectations. D
upvoted 1 times
GPena
3 years, 5 months ago
Recap this question, I will go with C. There is not need to add resources
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...