Exam CAPM topic 1 question 169 discussion

Actual exam question from PMI's CAPM
Question #: 169
Topic #: 1
[All CAPM Questions]

A project manager is in the process of working with stakeholders to meet their needs and expectations, and identifying and fostering communication and involvement. Which process does this typically represent?

  • A. Monitor Stakeholder Engagement
  • B. Monitor Communications
  • C. Manage Communications
  • D. Manage Stakeholder Engagement
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
adingmaki
1 month ago
Selected Answer: D
D. my baad.
upvoted 2 times
...
adingmaki
1 month, 1 week ago
C. Mechanics = Communications Strategy = Stakeholder
upvoted 1 times
...
anfacer
6 months, 1 week ago
Selected Answer: D
the phrase should end with "...foster appropiate stakeholder involvement". The word communication in the question is misleading
upvoted 1 times
...
MoonManBlue
2 years, 9 months ago
C-Manage Stakeholder Engagement
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago