Question #: 153
Topic #: 1
[All CAPM Questions]

A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated.
Which estimation method did the team use?

  • A. Rolling wave planning
  • B. Expert judgment
  • C. Decomposition
  • D. Data analysis
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
yolo_yogi
1 week ago
Selected Answer: D
There is no explicit mention of breakdown, Hence I believe decomp is not the correct option, I feel since "analyzed" is used the answer "data analysis" suites better. Data need not always be facts and figures, it can also be a situation or circumstance.
upvoted 1 times
...
MoonManBlue
2 months, 3 weeks ago
C-Decomposition
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago