Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 243 discussion

Actual exam question from PMI's CAPM
Question #: 243
Topic #: 1
[All CAPM Questions]

Which of the following are processes associated with Project Cost Management?

  • A. Develop Costs, Estimate Costs, Determine Budget, Control Costs
  • B. Develop Budget, Determine Budget, Determine Risks, Control Costs
  • C. Plan Cost Management, Estimate Costs, Determine Budget, Control Costs
  • D. Plan Budget Management, Determine Budget, Create Cost Accounts, Control Costs
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: C
C. Plan Cost Management, Estimate Costs, Determine Budget, Control Costs These are the core processes associated with Project Cost Management. Plan Cost Management involves defining how costs will be estimated, budgeted, monitored, and controlled. Estimate Costs involves developing an approximation of the monetary resources needed to complete project activities. Determine Budget aggregates the estimated costs of individual work packages and develops the overall project budget. Control Costs involves monitoring the project's spending, managing changes to the project budget, and generating forecasts of final project costs.
upvoted 1 times
...
041ba31
9 months, 1 week ago
C. Plan Cost Management, Estimate Costs, Determine Budget, Control Costs The processes associated with Project Cost Management are: 1. Plan Cost Management: This process involves defining how the project's cost management activities will be planned, structured, and executed throughout the project. 2. Estimate Costs: This process is focused on developing an estimation of the costs associated with the project activities and resources required to complete the project work. 3. Determine Budget: This process involves aggregating the estimated costs to establish a cost baseline for the project, which is used as a reference for project cost control. 4. Control Costs: This process focuses on monitoring, tracking, and managing project costs to ensure that they are within the approved budget and that any necessary corrective actions are taken if there are variations from the budget.
upvoted 2 times
...
MoonManBlue
3 years, 12 months ago
C is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...