A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?
if you have four main stakeholders, one project manager, and four other team members, then N = 9. Therefore, the number of communication channels available is Ch = 9 (9-1)/2 = 36.
The correct answer is B. 18.
The number of communication channels in a project is determined by the formula:
n(n-1)/2
where n is the number of stakeholders in the project.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
MoonManBlue
Highly Voted 4 years, 1 month agoarjune
Most Recent 7 months, 2 weeks agoAssad1981
1 year, 1 month agoNasser100
1 year, 3 months agoChymKuBoy
1 year, 5 months agobob523523
1 year, 7 months agobob523523
1 year, 7 months ago