One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?

  • A. It represents how and when the project will deliver the products, services, and results defined in the project scope
  • B. It creates a formal record of the project and shows the organizational commitment to the project
  • C. It describes how the scope will be defined, developed, monitored, controlled, and validated
  • D. It provides the needs of a stakeholders or stakeholder group
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: A
A. It represents how and when the project will deliver the products, services, and results defined in the project scope The detailed project schedule outlines the specific activities, their sequence, durations, and resource assignments required to achieve the project's objectives. It provides a clear roadmap for the project team, demonstrating how the project will be executed to deliver the expected outcomes within the defined scope
upvoted 1 times
...
041ba31
9 months, 1 week ago
A. It represents how and when the project will deliver the products, services, and results defined in the project scope The main purpose of the detailed project schedule is to represent how and when the project will deliver the products, services, and results defined in the project scope. It provides a timeline and sequence of activities, tasks, and milestones that outline the project's execution plan. This detailed plan helps project managers and the project team understand the sequence of work, resource requirements, dependencies, and critical paths necessary to complete the project on time and within scope.
upvoted 1 times
...
theplaceholder
1 year, 1 month ago
Selected Answer: A
hope you think about it
upvoted 1 times
...
[Removed]
1 year, 2 months ago
Selected Answer: A
A for sure. C speaks to scope only.
upvoted 2 times
...
PM01950
1 year, 3 months ago
Selected Answer: A
A is the true answer
upvoted 1 times
...
pbbade
1 year, 5 months ago
Selected Answer: A
is the correct answer
upvoted 1 times
...
anfacer
1 year, 9 months ago
Selected Answer: A
A is more suitable. C is the description of Scope Management Plan
upvoted 2 times
...
Haddie
3 years, 10 months ago
"A" should be the answer. This was explained under the key concepts for project schedule management pg674 of 6th edition. Literally, Answer A was verbatim.
upvoted 4 times
...
MoonManBlue
3 years, 12 months ago
That answer is the description of the Project Charter, so I don't know if the question is mistaken or what
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...