Exam CAPM topic 1 question 70 discussion

Actual exam question from PMI's CAPM
Question #: 70
Topic #: 1
[All CAPM Questions]

A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because it is a foreign location.
Which type of life cycle would the project manager use in this case?

  • A. Predictive life cycle
  • B. Waterfall life cycle
  • C. Hybrid life cycle
  • D. Product life cycle
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MoonManBlue
Highly Voted 3 years, 7 months ago
C-Hybrid Lifecycle
upvoted 8 times
...
anfacer
Highly Voted 1 year, 4 months ago
Selected Answer: C
predictive and waterfall are synonimes in PMBOK, that's why I dont think them are 100% correct. Correct for me is C as is predictive, we know the software and use, and adaptative, as the new language can bring some unexpected bugs
upvoted 5 times
...
theplaceholder
Most Recent 8 months, 2 weeks ago
Selected Answer: C
you need a combination of predictive and adaptive life cycles. thus, hybrid.
upvoted 1 times
...
sas2223
9 months, 3 weeks ago
Choice (A). Predictive Life cycle. See when you are expecting something to happen, it means you are predicting and anticipating a change. Secondly, the statement says that the software has been implemented at multiple branches domestically. So, there is no much changes in software as such. However, a foreign land has its own laws, which have to be complied by the participating businesses. For which we might have to do some changes. Now, what changes you have to make, will depend on rules, regulations, policies & laws of the foreign land. So, if you read those set of rules, you can predict what changes can creep in. Hence the correct answer is Predictive Life Cycle (choice A)
upvoted 2 times
...
Rocket20
9 months, 3 weeks ago
Selected Answer: C
Hybrid Lifecycle need flexibility for changes
upvoted 1 times
...
Raae
10 months, 2 weeks ago
Selected Answer: C
They mentioned there would be changes to the software but haven't confirmed what they are. I think hybrid as it gives the flexibility to deal with undefined requirements, unlike waterfall.
upvoted 2 times
...
ChymKuBoy
11 months, 1 week ago
Selected Answer: C
C for sure
upvoted 1 times
...
DJMCAPM
1 year, 2 months ago
C is correct
upvoted 2 times
...
MV87
1 year, 4 months ago
Selected Answer: C
Hybrid
upvoted 2 times
...
Gab2308
1 year, 5 months ago
Selected Answer: C
should be hybrid
upvoted 3 times
...
SUKHMANIIII
1 year, 7 months ago
Hybrid lifecycle
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago