Question #: 56
Topic #: 1
[All CAPM Questions]

A project manager is working on the communications management plan. Which of these documents are inputs to consider?

  • A. Stakeholder engagement plan and organizational process assets
  • B. Project schedule and stakeholder register
  • C. Quality management plan and risk register
  • D. Basis of estimates and scope baseline
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MoonManBlue
Highly Voted 4 years, 2 months ago
A-Stakeholder Engagement Plan and OPA's-Plan Communications Management-10.1
upvoted 6 times
...
Bokaku
Most Recent 2 months ago
Selected Answer: A
this is
upvoted 1 times
...
Fishell
1 year, 7 months ago
Selected Answer: A
Very easy by process of elimination if you know your terms.
upvoted 1 times
...
Navz
1 year, 10 months ago
Plan Communications Management—The process of developing an appropriate approach and plan for project communication activities based on the information needs of each stakeholder or group, available organizational assets, and the needs of the project.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...