C - Overall, the customer and sponsor have a continuous and collaborative involvement in project scope management activities in adaptive or agile life cycles. Their active participation ensures that the project stays aligned with their needs and expectations.
Tricky question, manual says continuolsy engagement in deliverablees as they are created, and mention Validate and Control Scope which are the end of an iteration.
I think is D.