Exam CAPM topic 1 question 216 discussion

Actual exam question from PMI's CAPM
Question #: 216
Topic #: 1
[All CAPM Questions]

The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?

  • A. Plan Resource Management
  • B. Estimate Activity Resources
  • C. Estimate Costs
  • D. Acquire Resources
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MoonManBlue
Highly Voted 3 years, 7 months ago
B-Estimate Activity Resources-9.2
upvoted 7 times
...
Dar87
Highly Voted 10 months, 3 weeks ago
Selected Answer: B
The key word here is resource
upvoted 5 times
...
theplaceholder
Most Recent 8 months, 1 week ago
Selected Answer: B
You have to read the question clearly. Estimate Costs is not in Project Resource Management.
upvoted 2 times
...
Sumbo
1 year, 3 months ago
Selected Answer: C
Parametric estimating is both a tool and technique of b and c
upvoted 2 times
...
limoncello
1 year, 3 months ago
Selected Answer: C
C or B - estimate costs 7.2.2.3 ; estimate activity resources 9.2.2.4
upvoted 2 times
...
missyi
1 year, 4 months ago
B. Estimate Activity Resources PMBOK 6th Ed. 9.2.2.4
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago