Exam CAPM topic 1 question 259 discussion

Actual exam question from PMI's CAPM
Question #: 259
Topic #: 1
[All CAPM Questions]

Which role does the project manager resemble best?

  • A. Orchestra conductor
  • B. Facilities supervisor
  • C. Functional manager
  • D. School principal
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: A
A. Orchestra conductor An orchestra conductor is the most accurate analogy for a project manager.   Both roles involve: Leading a team: Orchestrating the efforts of various individuals.   Coordinating multiple elements: Balancing different instruments or project components.   Maintaining a unified vision: Ensuring everyone works towards a common goal (a beautiful performance or successful project). Adapting to unexpected challenges: Handling unexpected changes in the music or project scope.
upvoted 1 times
...
041ba31
9 months, 1 week ago
A. Orchestra conductor The role of a project manager is often best likened to that of an orchestra conductor. Like a conductor, a project manager is responsible for coordinating and harmonizing the efforts of various individuals or team members (akin to musicians) to achieve a common goal or project objective. Both roles involve directing, orchestrating, and ensuring that all the elements come together to produce a successful performance or project outcome. This analogy captures the idea of the project manager guiding and leading the team toward project success through effective coordination and leadership.
upvoted 1 times
...
Pradnyasachin
9 months, 4 weeks ago
Selected Answer: A
Similar to an orchestra conductor, a project manager orchestrates various elements of a project, including team members, tasks, resources, timelines, and processes. They harmonize these components to ensure everything works together seamlessly toward achieving the project's goals, much like a conductor guides different musicians to create a cohesive musical performance.
upvoted 1 times
...
Rocket20
1 year, 2 months ago
Selected Answer: A
A. Orchestra Conductor, Please read 3.1 Overview - before the diamond points- sentence begins with " a simple analogy"
upvoted 1 times
...
[Removed]
1 year, 2 months ago
Selected Answer: A
A. Orchestra conductor Lots of moving parts across an entire orchestra but understands the pieces and helps them move together for one initiative as a whole collective goal, PMBOK pg 51
upvoted 1 times
...
PM01950
1 year, 3 months ago
Selected Answer: A
A-Orchestra Conductor 3.1 p.51
upvoted 1 times
...
adingmaki
1 year, 4 months ago
this is why you should read the PMBOK guide. The answer is orchestrator. Found in the beginning pages of the book
upvoted 2 times
...
anfacer
1 year, 9 months ago
Selected Answer: A
Orchestra
upvoted 3 times
...
missyi
1 year, 9 months ago
A - the project manager is compared to a conductor of a large orchestra. The project manager role is distinctly different from a functional manager.
upvoted 3 times
...
MoonManBlue
3 years, 12 months ago
A-Orchestra Conductor 3.1
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...