Deciding the phases of project life cycle would be considered a part of which of these knowledge areas?

  • A. Project Schedule Management
  • B. Project Scope Management
  • C. Project Resource Management
  • D. Project Integration Management
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
theplaceholder
8 months, 1 week ago
Selected Answer: D
charter > PIM
upvoted 1 times
...
garlicbread
9 months, 2 weeks ago
Selected Answer: D
Life cycles is part of the charter segment, I think
upvoted 1 times
...
Rocket20
9 months, 2 weeks ago
Selected Answer: D
D. Integration Management
upvoted 1 times
...
[Removed]
9 months, 3 weeks ago
Selected Answer: D
PMBOK Pg 74, definitely Integration, Though it is important to note that the development approach and project life cycle are sub-inputs to the Plan Scope Management process, they are tailoring considerations for Project Integration Management.
upvoted 2 times
...
pbbade
1 year ago
Selected Answer: D
is the correct answer
upvoted 1 times
...
UlrichIng
3 years, 6 months ago
Project Integration Management
upvoted 3 times
...
MoonManBlue
3 years, 7 months ago
D-Project Integration Management p.74
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago