At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?
C The overall scope of an adaptive project will be decomposed into a set of requirements and work to be performed, sometimes referred to as a product backlog. At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Three processes (Collect Requirements, Define Scope, and Create WBS) are repeated for each iteration page 131
Right answer is C:
At the beginning of an iteration, the team will work to
determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Three
processes (Collect Requirements, Define Scope, and Create WBS)
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
theplaceholder
8 months, 1 week agowwgk1980
9 months, 1 week agobramirezb593
10 months, 3 weeks agoadingmaki
11 months, 2 weeks agoHungdv
1 year, 1 month agomeg002
1 year, 4 months agolimoncello
1 year, 3 months agotheplaceholder
8 months, 1 week agoMoonManBlue
3 years, 7 months ago