exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 192 discussion

Actual exam question from PMI's CAPM
Question #: 192
Topic #: 1
[All CAPM Questions]

At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration.
Which of the following activities is done first?

  • A. Create Work Breakdown Structure (WBS)
  • B. Create Scope Baseline
  • C. Collect Requirements
  • D. Define Scope
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
theplaceholder
8 months, 1 week ago
Selected Answer: C
Collect Requirements is performed at the start of each iteration in an adaptive/agile environment.
upvoted 1 times
...
wwgk1980
9 months, 1 week ago
C The overall scope of an adaptive project will be decomposed into a set of requirements and work to be performed, sometimes referred to as a product backlog. At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Three processes (Collect Requirements, Define Scope, and Create WBS) are repeated for each iteration page 131
upvoted 1 times
...
bramirezb593
10 months, 3 weeks ago
Right answer is C: At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Three processes (Collect Requirements, Define Scope, and Create WBS)
upvoted 2 times
...
adingmaki
11 months, 2 weeks ago
A product backlog is a prioritized list of work for the development team that is derived from the roadmap and its requirements. definse scope it is
upvoted 1 times
...
Hungdv
1 year, 1 month ago
Define scope
upvoted 1 times
...
meg002
1 year, 4 months ago
Selected Answer: C
In order to define the scope, the requirements of the stakeholders must be collected first.
upvoted 3 times
limoncello
1 year, 3 months ago
but its at the beginning of an iteration, I assume the requirements have been cllected already so it should be D
upvoted 3 times
theplaceholder
8 months, 1 week ago
in an agile/adaptive project, the requirements would be collected during each iteration.
upvoted 3 times
...
...
...
MoonManBlue
3 years, 7 months ago
D-Define Scope p. 151
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago