Which of these is true of project integration management?

  • A. Project Integration Management is mandatory and more effective in larger projects
  • B. Project Integration Management and expert judgment are mutually exclusive
  • C. Project Integration Management is the responsibility of the project manager
  • D. Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
UlrichIng
Highly Voted 3 years, 6 months ago
C. Project Integration Management is the responsibility of the project manager
upvoted 7 times
...
alex903
Most Recent 9 months, 2 weeks ago
C. pg. 673
upvoted 1 times
...
MoonManBlue
3 years, 7 months ago
A-Project Integration Management is mandatory
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago