Question #: 127
Topic #: 1
[All CAPM Questions]

Which statement describes the relationship between Manage Quality process and Control Quality process?

  • A. Manage Quality is all about following planned processes and procedures for quality, while Control Quality is about making sure that the product which is produced conforms to customer specifications.
  • B. Control Quality is all about following planned process and procedures for quality, while Manage Quality is about making sure that the product which is produced conforms to customer specifications.
  • C. Manage Quality and Control Quality are the same.
  • D. Manage Quality is part of Quality Management and Control Quality is a subset of the Stakeholder Management Process group.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
theplaceholder
8 months, 1 week ago
Selected Answer: A
Correct
upvoted 1 times
...
MoonManBlue
3 years, 7 months ago
A appears to be the correct answer
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.