exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 77 discussion

Actual exam question from PMI's CAPM
Question #: 77
Topic #: 1
[All CAPM Questions]

A project receives budget approval, but the risk of extra costs is expected. Which of these inputs should the project manager check in order to make a qualitative risk analysis?

  • A. The risk management plan and the assumption log
  • B. Costs estimates and cost forecasts
  • C. The risk management plan and the basis of estimates
  • D. The assumption log and the project charter
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Pradnyasachin
1 day, 2 hours ago
Selected Answer: A
The risk management plan outlines the strategy for managing risks throughout the project, including the approach to identifying, assessing, and responding to risks.
upvoted 1 times
...
lauracecilia
5 months ago
A. 11.3.1.1, and 11.3.1.2.
upvoted 1 times
...
MFrankieG2022
11 months, 2 weeks ago
Key document here is the assumption log.
upvoted 4 times
...
MoonManBlue
3 years, 2 months ago
A-Risk Management Plan and Assumption Log
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago