A project receives budget approval, but the risk of extra costs is expected. Which of these inputs should the project manager check in order to make a qualitative risk analysis?
A.
The risk management plan and the assumption log
B.
Costs estimates and cost forecasts
C.
The risk management plan and the basis of estimates
The risk management plan outlines the strategy for managing risks throughout the project, including the approach to identifying, assessing, and responding to risks.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Pradnyasachin
1 day, 2 hours agolauracecilia
5 months agoMFrankieG2022
11 months, 2 weeks agoMoonManBlue
3 years, 2 months ago