Exam CAPM topic 1 question 40 discussion

Actual exam question from PMI's CAPM
Question #: 40
Topic #: 1
[All CAPM Questions]

In a preliminary meeting for a project, team members decide to execute the project with agile methodology. A finance team member wants to know how project cost will be determined at this early stage.
How will the project team determine project cost?

  • A. Use a lightweight cost estimation due to the nature of agile projects
  • B. Use a detailed cost estimation for agile projects
  • C. Retrieve a budget from a previous project and create a baseline for this project based on it
  • D. Use a detailed work breakdown structure (WBS) to get cost estimation
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ChymKuBoy
1 month ago
Selected Answer: A
A for sure
upvoted 1 times
...
UlrichIng
2 years, 8 months ago
A. Use a lightweight cost estimation due to the nature of agile projects
upvoted 3 times
...
MoonManBlue
2 years, 9 months ago
A is correct-Annex A1 p.92 6th edition
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago