Exam CAPM topic 1 question 33 discussion

Actual exam question from PMI's CAPM
Question #: 33
Topic #: 1
[All CAPM Questions]

Which of the following documents are created as part of Project Integration Management?

  • A. Project charter and project management plan
  • B. Communications management plan and scope management plan
  • C. Quality management plan and risk management plan
  • D. Project scope statement and communications management plan
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MoonManBlue
Highly Voted 3 years, 7 months ago
A-Project Charter and Project Management Plan
upvoted 6 times
...
theplaceholder
Most Recent 8 months, 2 weeks ago
Selected Answer: A
Correct
upvoted 1 times
...
Rocket20
9 months, 3 weeks ago
A. Project Charter is developed in integration See PMBOK chapter 4. 4.1 Develop Project Charter 4.2 Develop Project Management Plan Answer is A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago