How can a project manager represent a contingency reserve in the schedule?

  • A. Additional weeks of work to account for unknown-unknowns risks
  • B. Task duration estimates of the best case scenarios
  • C. Additional duration estimates in response to identified risks that have been accepted
  • D. Milestones representing the completion of deliverables
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
theplaceholder
8 months, 2 weeks ago
Selected Answer: C
Correct
upvoted 1 times
...
ale1231
2 years, 8 months ago
C. Additional duration estimates in response to identified risks that have been accepted
upvoted 3 times
...
Loraine40
3 years, 5 months ago
6th edition, of 702 Glossary - contingency reserve is time or money allocated in the schedule or cost baseline for known risks with active strategies.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel