Actual exam question from PMI's CAPM
Question #: 1
Topic #: 1
[All CAPM Questions]

Once the make-or-buy analysis is completed, which document defines the project delivery method?

  • A. Procurement statement of work (SOW)
  • B. Procurement strategy
  • C. Terms of reference
  • D. Change request
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
cadij
2 weeks, 6 days ago
Selected Answer: B
It is correct: Once the make-or-buy analysis is complete and the decision is made to acquire from outside the project, a procurement strategy should be identified. https://ln.run/p4sgr
upvoted 1 times
...
rosebethmiguel
3 months, 2 weeks ago
Selected Answer: B
The answer is B
upvoted 2 times
...
formosaHorus
5 months, 2 weeks ago
Selected Answer: B
The answer is B
upvoted 2 times
...
shubu2276
9 months ago
Selected Answer: B
B is correct. Once the make-or-buy analysis is completed, the document that defines the project delivery method is the "Procurement Strategy." The procurement strategy outlines how the project will obtain the necessary goods, services, or works. It includes decisions on whether to make in-house, buy from external sources, or use a combination of both approaches. The procurement strategy is a key component of the overall project management plan and helps guide the procurement activities throughout the project.
upvoted 2 times
...
Assad1981
1 year ago
The option B is coreect
upvoted 1 times
...
Cam77
1 year, 4 months ago
Selected Answer: B
The answer is B.
upvoted 2 times
...
ChymKuBoy
1 year, 5 months ago
B is done
upvoted 1 times
...
ThatAngie
1 year, 6 months ago
B! - answer
upvoted 1 times
...
jenza
1 year, 6 months ago
Selected Answer: B
B - woo!
upvoted 1 times
...
Raindrop79
1 year, 6 months ago
Pg 476 PMBOK 6th Procurement strategy
upvoted 2 times
...
bob523523
1 year, 7 months ago
B. Procurement strategy.
upvoted 2 times
...
ShashankJi
1 year, 8 months ago
B is the answer.
upvoted 2 times
...
FinnyNJeena
1 year, 9 months ago
B is correct
upvoted 2 times
...
Judmir
1 year, 10 months ago
Selected Answer: B
B is correct
upvoted 2 times
...
Judmir
1 year, 10 months ago
B i correct.
upvoted 2 times
...
anfacer
1 year, 10 months ago
B is correct: Review Chapter 12.1.3.2 - Procurement Strategy
upvoted 2 times
...
ld212903
1 year, 10 months ago
Selected Answer: B
12.1.3.2 - procurement strategy should be identified once make-or-buy analysis is complete
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago