Question #: 18
Topic #: 1
[All CAPM Questions]

With regard to a project manager's sphere of influence in a project, which of the following does the project manager influence most directly?

  • A. Suppliers
  • B. Customers
  • C. Governing bodies
  • D. Project team
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
theplaceholder
Highly Voted 2 years, 4 months ago
Selected Answer: D
this should hopefully be obvious
upvoted 8 times
...
emilianogalati
Most Recent 7 months, 3 weeks ago
Selected Answer: D
D This is due to the closest relationship a PM has with the team
upvoted 1 times
...
ChymKuBoy
1 year, 11 months ago
Selected Answer: D
D for sure
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago