Actual exam question from PMI's CAPM
Question #: 50
Topic #: 1
[All CAPM Questions]

After defining activities in project schedule management, which processes should a project manager follow?

  • A. Sequence Activities and Estimate Activity Durations
  • B. Estimate Activity Durations and Control Schedule
  • C. Develop Schedule and Control Schedule
  • D. Review Activities and Develop Schedule
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ChymKuBoy
1 month ago
Selected Answer: A
A for sure
upvoted 1 times
...
Saif93
2 months ago
Plan Schedule Mgmt - Define Activities - Sequence Activities- Estimate Activity Durations - Develop Schedule.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.