exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 24 discussion

Actual exam question from PMI's CAPM
Question #: 24
Topic #: 1
[All CAPM Questions]

Which tools and techniques will a project manager use to develop a project charter?

  • A. Project manager experience, expert judgment, scope statement, and meetings
  • B. Lessons learned database, interpersonal and team skills, cost baseline, and meetings
  • C. Expert judgment, data gathering, scope statement, schedule baseline, and meetings
  • D. Expert judgment, data gathering, interpersonal and team skills, and meetings
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ASCAPM
8 months ago
Selected Answer: D
D. Expert judgment, data gathering, interpersonal and team skills, and meetings The others options include Scope Baseline, Schedule Baseline or the Cost Baseline that are Outputs or Inputs not Tools and Techniques
upvoted 2 times
...
Cam77
10 months, 2 weeks ago
Selected Answer: D
D is correct. Ignore Ibrahim
upvoted 1 times
...
ChymKuBoy
11 months, 1 week ago
Selected Answer: D
D for sure. Expert judgment, data gathering, interpersonal and team skills, and meetings.
upvoted 2 times
...
Ibrahim_M
1 year ago
Selected Answer: A
Option D includes expert judgment, data gathering, interpersonal and team skills, and meetings, which are all important tools and techniques in developing a project charter. However, it does not include the scope statement, which is necessary for defining the project's objectives, goals, and boundaries. Therefore, option A is the correct answer as it includes all the necessary elements for developing a comprehensive project charter.
upvoted 1 times
AKCrause
1 year ago
They are asking for tools and techniques and the scope statement is an input, not a tool and technique
upvoted 3 times
...
...
Ibrahim_M
1 year ago
aNSWER SHOULD BE OPTION A
upvoted 1 times
...
anfacer
1 year, 4 months ago
Selected Answer: D
D, all other options requires baselines which are not created by then
upvoted 4 times
...
UlrichIng
3 years, 6 months ago
4.1 DEVELOP PROJECT CHARTER D. Expert judgment, data gathering, interpersonal and team skills, and meetings
upvoted 3 times
...
MoonManBlue
3 years, 7 months ago
D-Expert Judgement, Data Gathering, Interpersonal and team skills, Meetings 4.1
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago