D. Expert judgment, data gathering, interpersonal and team skills, and meetings
The others options include Scope Baseline, Schedule Baseline or the Cost Baseline that are Outputs or Inputs not Tools and Techniques
Option D includes expert judgment, data gathering, interpersonal and team skills, and meetings, which are all important tools and techniques in developing a project charter. However, it does not include the scope statement, which is necessary for defining the project's objectives, goals, and boundaries. Therefore, option A is the correct answer as it includes all the necessary elements for developing a comprehensive project charter.
D-Expert Judgement, Data Gathering, Interpersonal and team skills, Meetings 4.1
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ASCAPM
8 months agoCam77
10 months, 2 weeks agoChymKuBoy
11 months, 1 week agoIbrahim_M
1 year agoAKCrause
1 year agoIbrahim_M
1 year agoanfacer
1 year, 4 months agoUlrichIng
3 years, 6 months agoMoonManBlue
3 years, 7 months ago