exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 115 discussion

Actual exam question from PMI's CAPM
Question #: 115
Topic #: 1
[All CAPM Questions]

Which action should the project manager take after the team finishes executing the scope?

  • A. Verify the deliverables to ensure that they are correct and meet the customer's satisfaction.
  • B. Accept all the deliverables and deliver them to the customer for final acceptance.
  • C. Conduct a joint session with the customer, change the deliverables, and then request approval.
  • D. Check that all change requests were implemented and release deliverables to the customer.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
theplaceholder
8 months, 2 weeks ago
Selected Answer: A
Correct
upvoted 1 times
...
MoonManBlue
3 years, 7 months ago
Should be A, but Verify Deliverables was removed from the current edition
upvoted 1 times
MoonManBlue
3 years, 7 months ago
NM I was wrong
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago