exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 37 discussion

Actual exam question from PMI's PMI-ACP
Question #: 37
Topic #: 1
[All PMI-ACP Questions]

Two similar stories, A and B, are estimated at 3 story points. Story C, estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.
What should the agile practitioner do?

  • A. Assign story B more than 8 story points so to provide a better estimate
  • B. Add points to story B's iteration to account for the error but keep story B at 3 points
  • C. Assign more resources to story B to bring it in line with the estimate
  • D. Re-estimate all stories including values for A, B and C
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
snow5
Highly Voted 3 years, 11 months ago
A& C already completed so useless to re- estame them again. A is the correct answer
upvoted 8 times
srv3
3 years, 10 months ago
I agree. It is bad practice to reestimate completed stories. Also there is no reason to reestimate "C task". So D is not the best answer. A is correct answer.
upvoted 3 times
...
astrologic
2 years, 9 months ago
story A took much longer than story C, may be A = 3 and C = 2 or A = 5 and C = 4, so A not correct
upvoted 1 times
...
...
Notmeforsure
Most Recent 7 months, 3 weeks ago
Selected Answer: D
A and B are similar stories, and not "same" stories. So although A & C are already completed, reviewing what went wrong during estimation(retrospective), and re-estimating all the stories would be the right approach.
upvoted 1 times
...
chlaithem
9 months, 2 weeks ago
Selected Answer: D
A. Increased points for B: This assumes the error applies only to story A and B will be similar, which might not be true. Overestimation can lead to under-delivering in other areas. B. Add points to current iteration: This doesn't address the underlying reason for the discrepancy and doesn't improve future estimations. C. Assign more resources: Throwing resources at a potentially inaccurate estimate is inefficient and doesn't guarantee faster completion.
upvoted 1 times
...
itsmewajid
10 months, 3 weeks ago
Option D Estimate Activity Durations: This process emphasizes the need to update estimates throughout the project based on actual performance data and align with continuous improvement.
upvoted 1 times
...
Imrangoshi
1 year, 1 month ago
Selected Answer: D
D is the Correct Answer
upvoted 1 times
...
Siwana
1 year, 4 months ago
Selected Answer: A
Histórias concluídas não estimadas. Fico com A
upvoted 1 times
...
Minhha3
1 year, 6 months ago
Vote D
upvoted 1 times
...
Petrevski
1 year, 7 months ago
Selected Answer: D
Confusing question. D seem more realistic. A - "Story A took much longer than story C" How much? Assign story B more than 8? How much? Meaning could assign: 12, 20, 40? So undefined option. D - Adaptation based on empiricism in practice, but Scrum Master cannot re-estimate, the team can do.
upvoted 1 times
...
Smokeyofficiial
1 year, 7 months ago
Option D. Re-estimate all stories including values for A, B and C. This aligns with the Agile principle of "Continuous improvement" and the Agile practice of "Adapt and adjust." After discovering that the initial estimates were inaccurate, the team should re-estimate all stories, including A, B, and C, to reflect the actual time required to complete them. This enables the team to adjust their planning and improve their estimation accuracy for future sprints. Additionally, the team can identify any issues that contributed to the inaccurate estimate for story A and take steps to address those issues to prevent similar problems in the future.
upvoted 2 times
...
Holly2023
1 year, 8 months ago
Selected Answer: D
I vote for D. Re-estimate to re-establish baselines again
upvoted 1 times
...
InvisibleBeing
1 year, 9 months ago
Selected Answer: A
Changing my answer to A. I do not like the question; the agile manager has no authority to update the product backlog or the sprint backlog. Stories are estimated by the development team and the Agile coach is not the right person to update the story points. The question is asking about what the agile practitioner should do. Out of the given answers, A is more appropriate as there is no benefit in re-estimating completed stories from the previous sprint.
upvoted 1 times
...
InvisibleBeing
1 year, 9 months ago
Selected Answer: D
I am going with D. All other options talk about "Assigning". Scrum Master or an Agile Manager does not assign anything to agile teams. Agile teams are self-organizing and self-managing, he/she only facilitates discussion and coach agile best.
upvoted 1 times
InvisibleBeing
1 year, 9 months ago
I do not like the question. After further analysis, I am changing my answer to A. Even though the Agile-Coach cannot do anything or change story points without consulting with the team, there really is no point in re-estimating completed stories. This question is an example of empiricism.
upvoted 1 times
...
...
anttan
2 years, 1 month ago
How can A be the correct answer, as it's assumed that A is underestimated. Yes A (3 points) took longer to complete than C (8 points), what if it's C being grossly overestimated? C could be 1 point in reality, and hence A at 3 points is still correct.
upvoted 1 times
...
Alb65
2 years, 1 month ago
A is correct for me A similar to B , A took more time than C means B should be assigned more than 8 points
upvoted 1 times
...
richck102
2 years, 3 months ago
i vote A
upvoted 1 times
...
thuha1704
2 years, 7 months ago
I choose A
upvoted 2 times
...
Oshera
2 years, 10 months ago
D is the Answer. Once estimated a story points can not be changed. If the task is found to be too big it can be broken down into smaller pieces but the points remain the same.
upvoted 1 times
Oshera
2 years, 10 months ago
C is the answer error before.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago