You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule milestones?
Suggested Answer:D🗳️
Templates are used to identify the typical schedule milestones in the Define Activity process. The tools and techniques used in defining the activity process are as follows: Decomposition: It is used to further divide the project work package into a more smaller and convenient form called activities. Rolling Wave Planning: It is a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of WBS. Templates: It is an activity list or a part of the activity list taken from the previous project and used in a new project. Expert Judgement: The skilled members in a project team or other experts who develop project scope statements can help provide knowledge in defining activities.
Templates is not a T&T in any scheduling activity, the correct answer is Expert Judgement
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PMI-SP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
lucksuman
8 months agoMopar
1 year, 7 months ago