Question #: 11
Topic #: 2
[All PMI-SP Questions]

Which of the following is an output of the Identify Stakeholders process?

  • A. Scope baseline
  • B. Project scope statement
  • C. Project charter
  • D. Stakeholder register
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
The Identify Stakeholders process identifies all people or organizations that are impacted by the project. It also documents relevant information regarding their interests, involvement, and impact on project success. Stakeholder register and stakeholder management strategy are outputs of this process.
Incorrect Answers:
A: Scope baseline is one of the outputs of the Create Work Breakdown Structure (WBS) process.
B: Project scope statement is one of the outputs of the Define Scope process.
C: Project charter is one of the inputs of the Identify Stakeholders process.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Mopar
7 months, 3 weeks ago
Repeated question.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago