Exam PMI-SP topic 1 question 61 discussion

Actual exam question from PMI's PMI-SP
Question #: 61
Topic #: 1
[All PMI-SP Questions]

Harry works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, he has spent $725,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. What is the estimate at completion for this project that Harry will need to report to management?

  • A. $1,312,504
  • B. $787,504
  • C. $1,812,498
  • D. $725,000
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
The estimate at completion can be calculated by dividing the budget at completion by the cost performance index. Here,

CPI =EV/AC -
= (0.40*2,208,456)/725000
= 1.21846

EAC = BAC/CPI -
= 2,208,456/1.21846
= 1,812,498
What is Estimate at Completion (EAC)? Estimate at Completion (EAC) is a field that displays the final cost of the project including the actual costs and the forecast of remaining costs based on the cost performance index (CPI) so far. The formula used to calculate this estimate is as follows: ACWP+(BAC-BCWP)/CPI

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
aleemulislam
7 months, 4 weeks ago
As per the question, management seems worried that the project is over-budget, however as per the CPI & answer the project is under-budget.
upvoted 1 times
Mopar
7 months, 3 weeks ago
That's not the question, the question is that is the estimate at completion...
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago