exam questions

Exam PMI-SP All Questions

View all questions & answers for the PMI-SP exam

Exam PMI-SP topic 2 question 188 discussion

Actual exam question from PMI's PMI-SP
Question #: 188
Topic #: 2
[All PMI-SP Questions]

Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information, what is the estimate at completion for the NNQ Project?

  • A. -$98,217.78
  • B. -$44,198
  • C. $441,025.64
  • D. $243,219.78
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
The estimate at completion (EAC) formula is the Budget at Completion (BAC)/Cost Performance Index (CPI). In this instance, the CPI is .78 and the BAC is
$344,000. Cathy's project isn't doing too well.
Incorrect Answers:
A: This value represents the negative value the project will have once all the work is completed.
B: This value represents the negative cost variance.
D: This value represents the estimate to complete for the project.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ed55bcd
8 months, 1 week ago
EAC formula: EAC= AC+[BAC-EV]/CPI
upvoted 1 times
...
Mopar
4 years, 2 months ago
The explanation has nothing to do with the answer. (198998/45)*100
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago