Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 2 discussion

Actual exam question from PMI's PMI-ACP
Question #: 2
Topic #: 1
[All PMI-ACP Questions]

Midway through a sprint, the scrum master identifies that reassigning a certain task could help the team meet its sprint's goals.
What should the scrum master do next?

  • A. Alert the team that sprint goals might not be met and create an alternative plan
  • B. Obtain team buy-in to perform modifications to the sprint backlog
  • C. Have the sprint proceed as planned
  • D. Ask the team to decide if the task should be reassigned
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
navingthomas
Highly Voted 4 years, 1 month ago
The development team is responsible for the success of the sprint. Scrum master only facilitates... also creating an alternative plan during the sprint is not a good option. The team should decide whether to reassign the task. I will go with option D
upvoted 12 times
...
AmatullahSulaiman
Most Recent 1 month, 3 weeks ago
Selected Answer: C
No altering will be allowed during the sprint.
upvoted 1 times
...
FaisalK76
7 months, 2 weeks ago
Selected Answer: D
Agile is all about collaboration and discussing with every team member. A SM should put it to the team to decide on way forward.
upvoted 1 times
...
latigo
8 months, 1 week ago
1 vote for D
upvoted 1 times
...
Nervys
11 months ago
I vote D
upvoted 1 times
...
Imrangoshi
1 year, 2 months ago
Selected Answer: C
C is the correct answer
upvoted 1 times
...
Agile_Dario_Conde
1 year, 6 months ago
Selected Answer: D
D represents a servant leader
upvoted 1 times
...
Runako
1 year, 6 months ago
While it can be valuable to gather input from the team and consider their perspectives, it's important to note that decision-making in Scrum is typically based on collaboration and achieving a consensus rather than a strict majority vote. The Scrum framework emphasizes self-organization and encourages the team to collectively make decisions.
upvoted 1 times
...
cutri89
1 year, 8 months ago
Selected Answer: D
team have to decide
upvoted 1 times
...
Petrevski
1 year, 8 months ago
А/B - not an option C - sprint can be changed as long as the sprint goal is not endangered D - let the team decide, as self-organized unit
upvoted 2 times
...
faisalfaisal
1 year, 8 months ago
Selected Answer: D
.......................................................................................................
upvoted 1 times
...
TonyMai92
1 year, 9 months ago
Selected Answer: D
Let the team decides the way to complete these jobs. The SM can comment but not direct the dev plan.
upvoted 1 times
...
Sencaoco
1 year, 9 months ago
Selected Answer: D
Self organize team so scrum master only need to ask team to dicide among developers team
upvoted 1 times
...
InvisibleBeing
1 year, 10 months ago
Selected Answer: D
D is correct. Just like others have said, it is not the Scrum Master who assigns or reassigns tasks. It is the development team's responsibility (self-managing and self-organizing).
upvoted 2 times
...
Topajeugibu
2 years ago
Selected Answer: D
D is correct
upvoted 1 times
...
richck102
2 years, 4 months ago
D sure
upvoted 1 times
...
KisKat
2 years, 6 months ago
The SM can not create an alternative plan, only the Dev team can, that is why D is better answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...