Midway through a sprint, the scrum master identifies that reassigning a certain task could help the team meet its sprint's goals. What should the scrum master do next?
A.
Alert the team that sprint goals might not be met and create an alternative plan
B.
Obtain team buy-in to perform modifications to the sprint backlog
C.
Have the sprint proceed as planned
D.
Ask the team to decide if the task should be reassigned
The development team is responsible for the success of the sprint. Scrum master only facilitates... also creating an alternative plan during the sprint is not a good option. The team should decide whether to reassign the task. I will go with option D
While it can be valuable to gather input from the team and consider their perspectives, it's important to note that decision-making in Scrum is typically based on collaboration and achieving a consensus rather than a strict majority vote. The Scrum framework emphasizes self-organization and encourages the team to collectively make decisions.
D is correct.
Just like others have said, it is not the Scrum Master who assigns or reassigns tasks. It is the development team's responsibility (self-managing and self-organizing).
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
navingthomas
Highly Voted 4 years, 1 month agoAmatullahSulaiman
Most Recent 1 month, 3 weeks agoFaisalK76
7 months, 2 weeks agolatigo
8 months, 1 week agoNervys
11 months agoImrangoshi
1 year, 2 months agoAgile_Dario_Conde
1 year, 6 months agoRunako
1 year, 6 months agocutri89
1 year, 8 months agoPetrevski
1 year, 8 months agofaisalfaisal
1 year, 8 months agoTonyMai92
1 year, 9 months agoSencaoco
1 year, 9 months agoInvisibleBeing
1 year, 10 months agoTopajeugibu
2 years agorichck102
2 years, 4 months agoKisKat
2 years, 6 months ago