Exam PMI-ACP topic 1 question 106 discussion

Actual exam question from PMI's PMI-ACP
Question #: 106
Topic #: 1
[All PMI-ACP Questions]

An agile project manager is planning the initial scope, schedule, and cost range estimates on a new project. The team will be using Kanban to control work.
What metrics should the team use to measure performance?

  • A. Lead time, throughput, and due date performance
  • B. Work in progress limits, Kanban board, and time boxes
  • C. Work item types, sprint cadences, and defect classes
  • D. Burndown charts, scatter diagrams, and throughput
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Petrevski
7 months, 3 weeks ago
Selected Answer: A
A = correct B - The Kanban board is not a KPI + Kanban is non-timeboxed workflow C - Work item type is not a KPI D - Charts & diagrams are not KPIs, they should measure and show particular KPIs based on relevant parameters
upvoted 1 times
...
Raksim
11 months, 2 weeks ago
Kanban software doesn't have a Burndown chart because there is no predefined length of time in which a backlog should be finished.
upvoted 1 times
...
Minhha3
1 year ago
Vote A
upvoted 1 times
...
InvisibleBeing
1 year, 3 months ago
Selected Answer: A
A is correct
upvoted 1 times
...
nguyenducttk5
1 year, 9 months ago
Selected Answer: A
A is ok The question mentions metric
upvoted 1 times
...
richck102
1 year, 9 months ago
A sure
upvoted 1 times
...
JackNguyenvn
2 years ago
A is correct
upvoted 1 times
...
Alaaradwan
2 years, 9 months ago
A the answer
upvoted 1 times
...
HTTPS
2 years, 11 months ago
I would go for A.
upvoted 2 times
...
Athena75
3 years, 1 month ago
Answer is A https://getnave.com/blog/kanban-metrics/
upvoted 3 times
...
srv3
3 years, 4 months ago
I agree about A. Because all other is wrong. Answers B,C,D all contains something that is not a metric. Kanban board is a tool but not metric. Item type is also not a metric. Etc.
upvoted 3 times
...
snow5
3 years, 5 months ago
A is the correct answer. Lead time, throughput, and Due Date Performance¶. A brief explanation about Due Date performance: This report shows the percentage of items that were delivered on time and the average percentage delivery rate over time. This is useful for illustrating how predictable the system is. Due date performance with a low percentage provides evidence that there is an abundance of variability in the flow. The team should take corrective action or they will not be able to establish reasonable service agreements.
upvoted 2 times
...
GPena
3 years, 5 months ago
I think the correct answer is A
upvoted 1 times
...
Gnasher
3 years, 8 months ago
I think its A .https://www.acmagile.com/en/what-are-kanban-metrics/
upvoted 2 times
zvasanth1
3 years, 8 months ago
agreed +1
upvoted 1 times
...
...
zvasanth3
3 years, 8 months ago
A. Lead time, throughput, and due date performance B. Work in progress limits, Kanban board, and time boxes - There is no timebox in kanban C. Work item types, sprint cadences, and defect classes- There is no sprint cadence in kanban D. Burndown charts, scatter diagrams, and throughput A& B are closer to the answer
upvoted 3 times
zvasanth1
3 years, 8 months ago
no Burndown charts in kanban because no time box
upvoted 1 times
...
...
zvasanth3
3 years, 8 months ago
The two Kanban metrics that best measure your team performance are cycle times (how fast work gets done) and throughput (how much work is delivered). https://getnave.com/blog/kanban-metrics/ Lead time - does not provide team performance Cycle time - provides the team performance
upvoted 3 times
zvasanth3
3 years, 8 months ago
WIP also helps
upvoted 1 times
zvasanth3
3 years, 8 months ago
The cycle time scatter plot is an adapted version of the well-known chart. It is revered in the Lean management world because it provides a very detailed picture of one of the key metrics in Lean – cycle time https://kanbanize.com/kanban-resources/kanban-analytics/cycle-time-scatter-plot
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago