exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 318 discussion

Actual exam question from PMI's CAPM
Question #: 318
Topic #: 1
[All CAPM Questions]

A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?

  • A. Prepare a WBS for immediate tasks in the plan to work package level for duration and cost estimates.
  • B. Prepare a work breakdown structure (WBS) to include each deliverable with a target duration and cost estimate.
  • C. Prepare a WBS with task sequencing and detail the duration and cost estimates.
  • D. Prepare a WBS to work package level to effectively manage duration and cost estimates.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
8a6d137
2 days, 3 hours ago
Selected Answer: D
Creating a Work Breakdown Structure (WBS) to the work package level is the right approach for decomposing the scope to enable detailed cost and duration estimates. Work packages are the lowest level of the WBS and represent the smallest units of work that can be effectively estimated in terms of cost and duration. By breaking down the scope into work packages, the project team can accurately estimate the costs and durations associated with each work package, allowing for more precise project planning and management.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago