Exam PMI-RMP topic 1 question 34 discussion

Actual exam question from PMI's PMI-RMP
Question #: 34
Topic #: 1
[All PMI-RMP Questions]

Due to lack of specific knowledge within a technical domain, the project manager decides an expert from outside the organization should be invited into the project to identify and analyze risks. The project manager understands that the risk management process has many benefits, but it will also have clear costs.
Which of the following should the project manager do?

  • A. Identify internal resources with proper knowledge, and keep costs down.
  • B. Hire experts as needed.
  • C. Hire a specialized risk analysis consulting company.
  • D. Determine that the benefits outweigh the costs where risk is involved.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago