exam questions

Exam PMI-SP All Questions

View all questions & answers for the PMI-SP exam

Exam PMI-SP topic 2 question 101 discussion

Actual exam question from PMI's PMI-SP
Question #: 101
Topic #: 2
[All PMI-SP Questions]

You work as the project manager for Blue Well Inc. You are working with your project team to schedule the days the project work will take place. You have created a project network diagram as shown in the figure:

Based on this diagram, find out the earliest day on which Activity G can be started.

  • A. Day 13
  • B. Day 7
  • C. Day 22
  • D. Day 17
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
The earliest Activity G can start is Day 17. This is because activities A, D, C, and F must all be completed before Activity G can start.
Incorrect Answers:
A: Day 13 does not account for Activity F since Activity F is also a predecessor to Activity G.
B: Day 7 is not a valid answer.
C: Day 22 is the earliest Activity G can finish.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
jalaljaafarsalman
11 months, 3 weeks ago
The earliest day on which Activity G can be started is 16
upvoted 1 times
Mopar
7 months, 3 weeks ago
No. Day 16 is when Activity F ends.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago