exam questions

Exam PMI-SP All Questions

View all questions & answers for the PMI-SP exam

Exam PMI-SP topic 2 question 92 discussion

Actual exam question from PMI's PMI-SP
Question #: 92
Topic #: 2
[All PMI-SP Questions]

Allen is the project manager for his organization. He is reviewing the resource requirements for his organization. He has discovered that his project needs Henry, the application developer, for two months, but Henry has a conflict and is already scheduled with another project manager in the organization. This is an example of which of the following?

  • A. Resource competition
  • B. Matrix organization
  • C. Resource requirement
  • D. Resource constraint
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Because this project needs the specific resource of Henry, the application developer, and Henry is not available, it is considered as a resource constraint. Recall that a constraint is anything that limits the project manager's option.
Incorrect Answers:
A: While there may be some competition for skilled resources, such as Henry, the application developer, it is not the best answer for this question.
B: This is likely a matrix organization, but it is not the best answer for this question.
C: A resource requirement is simply the need for an application developer.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ed55bcd
7 months, 2 weeks ago
Resource Constraint: Here is why, the company has the recourse, but not available at the time the department needs him.
upvoted 1 times
...
Chikhalsouk
2 years, 9 months ago
Resource requirement
upvoted 1 times
...
Alisonw
3 years, 10 months ago
This is a constraint as he is not available, planning will now be constrained to when he is
upvoted 2 times
...
jalaljaafarsalman
4 years, 5 months ago
This is not a resource constraint, it is resource requirement
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago