Exam PMI-SP topic 2 question 36 discussion

Actual exam question from PMI's PMI-SP
Question #: 36
Topic #: 2
[All PMI-SP Questions]

You are working with your project team to control the project schedule. You will need five inputs to this process throughout your project. Which one of the following is an output of the project schedule control, and NOT an input?

  • A. Work performance information
  • B. Project schedule
  • C. Project management plan
  • D. Work performance measurements
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Work performance measurements are created from the work performance information. WPMs are an output of Control schedule, Control cost, and Control scope processes, which are monitoring and controlling processes. WPMs consist of planned versus actual performance indicators with respect to scope, schedule, and cost. They are documented and communicated to the stakeholders and are used to make project activity metrics, such as the following: Planned vs. Actual
Technical performance and Scope performance Planned vs. Actual Schedule performance Planned vs. Actual Cost performance
Incorrect Answers:
A: Work performance information is an input to the control schedule process and includes information on project progress and activity start and finish information.
B: The project schedule is an input to the control schedule process.
C: The project management plan is an input to the control schedule process.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
[Removed]
8 months, 2 weeks ago
CISA, CISM, CRISC, CGEIT, CompTIA, CCNA, PMP, PMI-RMP, PMI-ACP, PMI-PBA, PMI-CAPM, SCRUM, Azure, AWS, Salesforce, ITIL, ISTQB, CLOUD, CEHv12, CCISO, GMAT, Six-sigma, SAP, Oracle, ISO... Get Certified with great ease. 100% pass guarantee. Exam support / proxy PAYMENT ONLY AFTER PASSING WhatsApp: +1(940) 268-5570
upvoted 1 times
...
ed55bcd
8 months, 2 weeks ago
Project Schedule the correct answer?
upvoted 1 times
...
HJPMI
8 months, 3 weeks ago
Work performance information is output of Control Schedule (Kindly correct it).
upvoted 1 times
...
Mopar
4 years, 3 months ago
Outputs of Control Schedule: Work performance information Schedule Forecasts Change Requests Project Management Plan Updates Project document Updates
upvoted 2 times
...
jalaljaafarsalman
4 years, 5 months ago
Work performance data is an input to control schedule and contains data on project status such as which activities have started, their progress (e.g., actual duration, remaining duration, and physical percent complete), and which activities have finished. (PMBOK, P. 225) Work performance information is an output of control schedule and includes information on how the project work is performing compared to the schedule baseline. Variances in the start and finish dates and the durations can be calculated at the work package level and control account level. For projects using earned value analysis, the (SV) and (SPI) are documented for inclusion in work performance reports. (PMBOK, P. 228)
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago