Question #: 120
Topic #: 1
[All PMI-PBA Questions]

Which of the following is a method for requirements change control?

  • A. Baselining
  • B. Scope analysis
  • C. Communication management
  • D. Requirements management
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
64458f1
6 days, 3 hours ago
Selected Answer: D
Requirements management
upvoted 1 times
...
Ecomexpert
1 week ago
Selected Answer: A
Requirements management - is used to manage requirements in a single repository
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel