exam questions

Exam PMI-PBA All Questions

View all questions & answers for the PMI-PBA exam

Exam PMI-PBA topic 1 question 52 discussion

Actual exam question from PMI's PMI-PBA
Question #: 52
Topic #: 1
[All PMI-PBA Questions]

A new project’s goal is to replace an existing system. What is an input into solution evaluation and decision making in this context?

  • A. Cost-benefit analysis of the existing system
  • B. New solution design specification
  • C. Customer metrics on the existing system
  • D. Technical readiness of the development team
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Ecomexpert
1 week, 3 days ago
Selected Answer: C
Customer metrics provides input to the solution evaluation process
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel