Exam PfMP topic 1 question 210 discussion

Actual exam question from PMI's PfMP
Question #: 210
Topic #: 1
[All PfMP Questions]

Which tool or technique should the portfolio manager use to identify areas in which the portfolio may be underperforming in financially intangible ways?

  • A. Risk earned value management (EVM)
  • B. Cost-benefit analysis
  • C. Value measurement
  • D. Scoring models
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tpkhoa
2 months, 1 week ago
Selected Answer: C
I chose C. Scoring models → While useful for ranking portfolio components, they are not specifically designed to assess financially intangible underperformance.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel