exam questions

Exam PMI-PBA All Questions

View all questions & answers for the PMI-PBA exam

Exam PMI-PBA topic 1 question 45 discussion

Actual exam question from PMI's PMI-PBA
Question #: 45
Topic #: 1
[All PMI-PBA Questions]

A major stakeholder wants to know how the implementation of new features in the development of a product is progressing. Which of the following should be reported to the stakeholder?

  • A. Number of requirements tested and approved
  • B. Distribution of project changes
  • C. Requirements status during the project development cycle
  • D. Number of requirements approved vs. number of requirements rejected
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Ecomexpert
1 week, 3 days ago
Selected Answer: C
Requirements status shall show the status of the Requirements. The status can be tracked any Requirement management software or even in traceability matrix
upvoted 1 times
...
Otus
1 month ago
Selected Answer: C
The requirements status during the project development cycle provides a clear picture of how new features are progressing. It tracks the movement of requirements through different stages—such as defined, approved, in development, tested, and implemented—giving stakeholders real-time insights into the implementation process.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.