A major stakeholder wants to know how the implementation of new features in the development of a product is progressing. Which of the following should be reported to the stakeholder?
A.
Number of requirements tested and approved
B.
Distribution of project changes
C.
Requirements status during the project development cycle
D.
Number of requirements approved vs. number of requirements rejected
Requirements status shall show the status of the Requirements.
The status can be tracked any Requirement management software or even in traceability matrix
The requirements status during the project development cycle provides a clear picture of how new features are progressing. It tracks the movement of requirements through different stages—such as defined, approved, in development, tested, and implemented—giving stakeholders real-time insights into the implementation process.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Ecomexpert
1Â week, 3Â days agoOtus
1Â month ago