Which of the following can a project manager conduct if they have a stakeholder who is unresponsive and/or unsupportive?

  • A. Communication style assessment
  • B. Push communications
  • C. Pull communications
  • D. Interactive communications
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Jtic
2 weeks, 3 days ago
Selected Answer: B
B. Push communications: This approach involves sending information directly to stakeholders without expecting an immediate response. Examples include emails, reports, or newsletters. This is effective for ensuring that the stakeholder receives the necessary information, even if they do not engage actively. In cases of unresponsiveness, push communications can be an effective way to keep the stakeholder informed
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago