Some engineers are completing an activity that will alert the project team if there is a risk of requiring additional effort to complete the project. What should the risk manager do in case the trigger arises?

  • A. Request a reserves increase.
  • B. Update the risk response plan.
  • C. Activate the contingency plan.
  • D. Add the alert to the risk register.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Amakancn
4 months, 3 weeks ago
Selected Answer: C
If the risk has materialized and is causing an issue, the appropriate action is to activate the contingency plan. Contingency plans are pre-identified actions designed to mitigate the impact of a known risk if it occurs. Since the situation suggests a reactive response to an occurring risk, following the contingency plan is the most logical step.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago