Some engineers are completing an activity that will alert the project team if there is a risk of requiring additional effort to complete the project. What should the risk manager do in case the trigger arises?
If the risk has materialized and is causing an issue, the appropriate action is to activate the contingency plan. Contingency plans are pre-identified actions designed to mitigate the impact of a known risk if it occurs. Since the situation suggests a reactive response to an occurring risk, following the contingency plan is the most logical step.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMI-RMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Amakancn
4 months, 3 weeks ago